US 176

US 176 will undergo operational improvements for safety and traffic flow from I-26 to I-585 / SC 56 split with intersection improvements at John Dodd Rd, Belcher Rd, and Springfield Rd. See maps below for details.

Schedule:

  • Preliminary Engineering began Winter 2009-2010 and is scheduled to be complete Autumn 2016
  • Right of Way began Autumn 2015 and is scheduled to be complete Autumn 2016
  • Construction is scheduled to begin Winter 2016-2017 and will be complete Spring 2018




Update (June 2015):

  • PE is approximately 65% complete
  • ROW Obligation is scheduled for Fall 2015
  • Construction Letting is scheduled for Fall 2016


Update (Feb 2016):

  • PE is approximately 75% complete
  • ROW Acquisition is underway
  • Construction Letting is scheduled for Fall 2016