S-30

SCDOT will be doing two intersection improvements north of Zion Hill Rd and south of Fernwood Glendale Rd (Clifton Glendale Rd).

Schedule:

  • Preliminary Engineering began Summer 2011 and is scheduled to be complete Autumn 2016
  • Right of Way began Winter 2015-2016 and is scheduled to be complete Autumn 2016
  • Construction is scheduled to begin Winter 2016-2017 and will be complete Spring 2018




Update (June 2015):

  • PE is approximately 30% complete
  • ROW Obligation is scheduled for late 2015
  • Construction Letting is scheduled for late 2016


Update (Feb 2016):

  • PE is approximately 75% complete
  • ROW Acquisition is underway
  • Construction Letting is scheduled for late 2016


Link to construction updates on the SCDOT website: Zion Hill / Clifton Glendale / Fernwood Glendale Rds