Old Furnace Rd Sidewalks

SCDOT will be constructing sidewalks on Old Furnace Rd (S-56) from North Spartanburg Sports Complex entrance (MP 1.45) towards the Boiling Springs Freshman Campus to Mason Rd (MP 4.33) near Boiling Springs High School.

Schedule:

  • Preliminary Engineering began Autumn 2013 and is scheduled to be complete Summer 2016
  • Right of Way began Spring 2015 and is scheduled to be complete Summer 2016
  • Construction was completed in 2017




Update (June 2015):

  • PE is approximately 70% complete
  • ROW Acquisition will begin Summer 2015
  • Utility Coordination is underway
  • Construction Letting is scheduled for Fall 2016


Update (Feb 2016):

  • PE is approximately 75% complete
  • ROW Acquisition is 90% complete
  • Utility Coordination is underway
  • Construction Letting is scheduled for Fall 2016


Update (Nov 2017):

  • PE is 100% complete
  • ROW Acquisition is 100% complete
  • Construction is substantially complete